1. Purpose
This work instruction describes the coding structures and numbering codes which apply to the identification of documents produced by Company on a project.
2. General
All Company project documents as listed in this procedure (section. 4.1 through 4.8) shall be numbered in accordance with this procedure.
Changes to any element of the project document number coding structure shall be made only with the approval of the Project Manager. The structure and coding is essentially fixed.
Client document number requirements are defined in the Project Procedure and Execution Manual (PPEM), (ref. 5.4).
If Client's document numbers are to be used, Company document numbers shall also be allocated and shall be put near to the title block of each document (ref. 5.3). The Company document number will be used for internal references, cost control system, filing and distribution purposes. Any proposed deviation shall be approved by the Project Manager.
Supplier documents will be numbered by the Supplier/Manufacturer/Subcontractor as stipulated and requested in the General Specification for Suppliers Furnished Documents.
Project Communications shall be numbered in accordance with the Project Procedure and Execution Manual and/or instructions.
2.1 Legend to Basic Document Numbering System
The following alpha/numeric characters are used in formatting a document number,
"AA" | — | A | — | NN | NN(NN) |
(1) | (2) | (3) | (4) |
(1) Alpha characters within the quotation marks refer to prefixes given to specific documents (e.g., “PP” for centrifugal pumps).
(2) One alpha character is shown as A.
(3) Two numeric characters are shown as NN.
(4) One or more characters between brackets are optional and depend on the type of document. If document numbers require segregation, dashes shall be shown. If no segregation is required, the document number shall be written without spacings.
3. Responsibilities
The Project Manager is responsible that for project documents this procedure is adhered to and that any deviation to the standard coding structure is approved. He is also responsible for defining any Clients document number requirements, (ref. 5.4).
The Lead Specialist Engineer is responsible for ensuring that project document numbers are assigned in accordance with this procedure (and Client document numbers, in accordance with the PPEM, if required).
4. Numbering of Documents
The Project Manager shall ensure that only unique document numbers will be allocated. Document numbers may only be allocated once. If documents are declared "void", the document number shall not be re-used.
4.1 Project Procedures
NNNN | — | "AA(A)" | — | NNN |
(1) | (2) | (3) |
A supplement to the Company standard procedures or a project dedicated procedure shall be numbered as follows:
(1) Project number | (2) As defined per project/proposal. |
(2) Prefix |
|
(3) Serial number |
|
Examples: | |
1111-PP-001 |
|
1111-PP-002 |
|
1111-PPE-001 |
|
4.2 Guides, Standards and Specifications
4.2.1 Company Guides, Standards and General Specifications
NNNN | — | “A(A)” | — | A(AN) | NN |
(1) | (2) | (3) | (4) |
A supplement to a company guide, standard and/or specification used for a project, or a new project dedicated guide, standard and/or specification, shall be numbered as follows:
(1) Project number |
|
(2) Type of document | |
- Engineering | DG - Design Guide DS - Design Standard EG - Engineering Guide ES - Engineering Standard SP - Specification |
- Others | G - Guide S - Standard |
(3) Project cost code |
|
UE1 - Engineering Process UE2 - Engineering Project UK0 - Project Management UK1 - Estimating UK2 - PMS Systems & Support UK3 - Cost Engineering UK4 - Planning & Scheduling UP1 - Purchasing UP2 - Inspection UP3 - VPC/Expediting |
|
(4) Serial number |
|
Examples: | |
1111-SP-UK001 | Specification for site QA control requirements for subcontractors |
1111-SP-K10 | Specification for instrument testing, calibration and acceptance |
4.2.2 Equipment, Material Specifications and Data Sheets
NNNN | — | “AA(A)” | — | AA | NN | NN(A) | /ANN |
(1) | (2) | (3) | (4) | (5) | (6) |
(1) Project Number |
|
|
(2) Type of Document |
|
|
EDS |
|
|
EMD |
|
|
EQS |
|
|
MDS |
|
|
NDS |
|
|
PDS |
|
|
SFD |
|
|
SP |
|
|
(3) Cost Code/stem sub |
|
|
CD |
|
|
PP |
|
|
GZ |
|
|
(4) Unit Number (if applicable) |
|
|
(5) Serial Number |
|
|
(6) Code/Serial Number |
|
|
Examples: | ||
1111-PDS-AS1201A |
|
|
1111-MDS-PP1102 |
|
|
1111-EQS-PP0001 |
|
Where drivers are ordered with the driven equipment, the data sheet for the driver is numbered as an additional sheet to the specification for the driven equipment.
e.g., | 1111-EMD-PP1102 |
Where drivers are ordered separately from the driven equipment, the driver data sheet shall be identified as for drivers supplied with the driven equipment.
Refer to section 4.2.5 for data sheet numbering of miscellaneous equipment belonging to package units.
4.2.3 Material Detailed Descriptions for Requisition Line Items (piping “C” account)
The technical descriptions and other pertinent technical details that refer to requisition line items are summarized in a document that shall be numbered “SP--- followed by the requisition number e.g.:
1111-SP-CD1001-B01
The requisition detail numbering system is further detailed in section 4.3.2.
4.2.4 Equipment, Material Specifications and Data Sheets for Control Systems
The Control Systems department produce equipment or material specifications using a word processing program. Such specifications may describe tagged equipment items or bulk materials. Tagged items are usually detailed in data sheets.
The material/equipment specification is named according to the naming convention for the pertinent requisition (see section 4.3.4) with an “S” suffix.
Data sheets are produced from a database program and are packaged as a single document. The document is named according to the pertinent requisition (see section 4.3.4) with a “T” suffix.
Examples: | |
11112001-KV0101 | typical control valve requisition |
11112001-KV0101S | associated material specification |
11112001-KV0101T | associated technical data sheet package. |
4.2.5 Package Unit Data Specifications
Data sheet numbers for supplier furnished data sheets shall include the tag number of the package extended with a code/serial number related to subject equipment.
Example: |
|
1111-EQS-PC1501 | Centrifugal Compressor PC1501 (Package Unit) |
1111-EMD-PC1501 | Main E-Driver PC1501 |
1111-NDS-PC1501 | Noise Data Sheet PC1501 |
1111-SFD-PC1501/E01 | E-Motors Lubrication Pump(s) |
1111-SFD-PC1501/E02 | E-Motors for Noisehood Fan(s) |
1111-SFD-PC1501/M01 | Lube Oil Reservoir |
1111-SFD-PC1501/P01 | Lubrication Pump(s) |
1111-SFD-PC1501/T01 | Intercooler for PC1501 |
1111-SFD-PC1501/T02 | Aftercooler for PC1501 |
1111-SFD-PC1501/T03 | Lube Oil Reservoir Heater(s) |
4.3 Requisitions
The arrangement below illustrates the basic structure of document numbers for requisitions. The structure is presented as a sequence of 4 blocks. Block 3 is not used for requisitions, but it is shown because the structure is essentially the same as for inquiries, (blanket) purchase orders and purchase order releases. For these documents block 3 is used.
NNNNNNNN ANNNN |
— | A(A)NNNN | (A)(AA)(N) | (ANN) |
(1) | (2) | (3) | (4) |
(1) Project charge number |
|
(2) Requisition number details |
|
For field Labor only, a single alpha character is used (see section 4.3.5). | |
Within the “U” account only “UJ” may be used. | |
The use of the numeric characters differs per discipline and is explained below (see section 4.3.1 thru 4.3.5). For certain disciplines, but not for piping, the first two numeric characters may be used to distinguish requisitions for different units (or other appropriate project subdivision). | |
The Project Manager shall instruct all involved parties as to whether or not requisitions are to be prepared separately by unit (or other appropriate project subdivision). | |
(3) Purchase order/inquiry indicator |
|
(4) Document suffix (piping requisitions only) |
|
Consecutive requisitions for bids have suffices: B01, B02 etc. | |
Consecutive requisitions for purchase (or bids and purchase) have suffices P01, P02 etc. | |
This suffix is also used to distinguish, if necessary, requisitions for different units (or other appropriate project subdivision). |
Examples: | |
11112001-PP0001 (1) (2) |
|
11112007-PP0001 (1) (2) |
|
11112001-CD1001-B01 (1) (2) (4) |
|
11112001-CD1001-P02 (1) (2) (4) |
|
4.3.1 Requisition Number Details Mechanical Equipment
The Project Manager shall instruct all involved parties whether or not requisitions are to be prepared for each unit.
Equipment items are grouped for initial requisitioning purposes into logical groups according to size, material, type, etc. according to the basic cost codes (see Project Cost Code”).
During bid evaluation the decision may be made to split the requisition between two or more suppliers. The initial requisition will then be adjusted and (a) new requisition(s) shall be prepared to cover the items that will be ordered from other supplier(s).
Example | ||||
Item | ||||
Requisition | Issue | Description | Covering Items | |
To all selected suppliers A, B, etc. | TT2001 | 1 | Released for quotation | TT2001/2009/2013/ 2024/2026 |
For supplier "A" (covering most items) | TT2001 | 2 | Released for purchase | TT2009/2013/2024 |
For supplier "B" | TT2004* | 1 | Released for purchase | TT2001/2026 |
* TT2004 being the lowest available requisition number.
This requirement does not apply to bulk material requisitions.
4.3.2 Requisition Number Details for Piping “C” Account
The requisition numbers for the piping items are grouped into various components and materials.
For an index of standard requisition detail numbers reference is made to Attachment 2.
For an explanation of the basic structure of the requisition number details see section 4.3 block (2).
4.3.3 Requisition Number Details Electrical
The electrical requisitions shall in general be numbered as indicated in section 4.3.
The charge number shall be as defined for the project or proposal.
The requisition number details shall be a two character designation, starting with the stem account character “E” followed by a second stem sub character as per the standard Project Cost Code. The requisition numbers details are completed with four numeric characters. The first two shall be “00” unless the project/proposal requires some sort of split of the requisition, such as by area, unit or vendor.
The Company standard stem and stem sub characters for the electrical discipline are as follows:
|
Transformers |
|
Switchgears and MCC’s |
|
Panels |
|
Cables |
|
Heating and Tracing |
|
Communication Systems |
|
Cathodic Protection |
|
Lighting Fixtures |
|
Miscellaneous Electrical Materials |
|
Special Electrical Equipment |
In case the project/proposal requires a split of the requisitions per area, unit or vendor then the first two numeric characters of the requisition number detail shall be used as the area or unit identification.
The electrical requisitions shall usually refer to the two following main related documents:
- the data sheets
- the specifications(s).
The data sheets and the specifications shall be listed in the “Attached or Referenced Document List” of the requisition and shall form an integral part of the requisition.
The data sheets and specifications shall be numbered in accordance with section 4.2.
4.3.4 Requisition Number Details Control Systems
Attachment 1 of the work instruction provides a representative list of standard control systems requisitions. The current standard list is maintained by the department in the “Control Systems Engineering Design Manual” as a printed copy of the electronic master list.
In general the nomenclature for control systems requisitions follows the format prescribed above with the following details.
Project Cost Code is a two character designation beginning with “K” (traditional designation for the department) followed by a character designating the type of equipment.
Examples: | KA (analyzers); | KF (flow measurement); | KV (valves); |
KS (safety relief); | KX (systems); | KT (temperature); etc. |
The next four places of the requisition number are numeric. The first two digits shall be ‘00’ unless the project requires some sort of split of the equipment account (such as by area, unit, or vendor). The final two digits define the core account.
Examples: | KA0017 |
|
KV0001 |
|
|
KF0001 |
|
If the project requires requisitions split between units, then the control valves requisitions might be:
- KV0101 for unit 100 and KV0201 for unit 200.
As a further example, if two vendors must be used to provide all the gas chromatographs, the requisition KA0017 for bids might be split to KA2017 for one vendor and KA1017 for the other vendor.
Control systems requisitions usually reference two main related documents:
- the detailed specification narrative or write-up that is a word processing document that shall be named according to the core requisition number with the character “S” suffixed (for Specification);
and, - the technical data sheets package is generated by the database systems and shall be named according to the core requisition number with the character “T” suffixed (for Technical Data Sheets). See section 4.2.
4.3.5 Requisition Number Details Field
LaborRequisitions for field labor usually cover work involving several Cost Codes. Listed below are the standard requisition numbers for some frequently occurring cases:
Requisition Number | |
Mechanical Works (Equipment Erection) | A 0001 ) |
Buildings | B 0001 ) |
Structural Steel Supply & Erect | D 0001 ) |
Electrical Installation | E 0001 ) |
Civil Work | J 0001 ) 0002, etc. |
Instrument Installation (refer Attachment I, sheet 4) | K 0001 ) |
Insulation | N 0001 ) |
Mechanical incl. Piping Prefab and Erection | M 0001 ) |
Painting | R 0001 ) |
Site Development | S 0001 ) |
0001, 0002 are sequence numbers. | |
Deviations from the above standard numbers shall be described in the Project Procedures and Execution Manual. |
4.4 Inquiries, (Blanket) Purchase Orders & Purchase Order Releases
The arrangement below illustrates the basic structure of document numbers for, inquiries, (blanket) purchase orders and purchase order releases on projects.
NNNNNNNN ANNNN | — | A(A)NNNN | (A)(AA)(N) | (ANN) |
(1) | (2) | (3) | (4) |
(1) Project charge number |
|
(2) Requisition number details |
|
If a purchase order or any inquiry covers more than one requisition, the purchase order/inquiry number shall be based on the lowest requisition number. (For combined piping requisitions covering more than one type of material, see example below.) | |
A purchase order for equipment/materials shall not combine requisitions with the first two (alpha) characters of the requisition number being unequal. (For example, an “MS” requisition and an “MR” requisition shall not be combined into one purchase order.) | |
(1) Purchase order inquiry indicator |
|
For inquiries the letters “RFQ” shall be used. | |
For a subsequent inquiry based on the same requisition to other suppliers with possibly a different bid closing date the characters RFQ1 shall be used. | |
(1) Document suffix (Blanket purchase order releases only) |
|
Examples: | |
11112001-PP0001RFQ (1) (2) (3) |
|
11112001-PP0001RFQ1 (1) (2) (3) |
|
11112001-PP0001A (1) (2) (3) |
|
11112001-CD0001A (1) (2) (3) |
|
11112001-CD0001A-R01 (1) (2) (3) (4) |
|
11112001-CD0001A-R02 (1) (2) (3) (4) |
|
4.4.1 Changes to Purchase Orders and Purchase Order Releases
Changes to purchase orders and blanket purchase orders shall be lettered "A", "B",... "Z", "AA", "AB" etc.
Revisions to Inquiries and release orders (to correct errors and omissions) shall be numbered 1, 2 etc.
Example: | |
11112001-PP0001A Change order B |
|
11112001-CD0001A-R01 revision 1 |
|
4.5 Drawings
4.5.1 Single Sheet Documents
NNNN | — | NNNN | NNN | A(A) | — | AN(N) |
(1) | (2) | (3) | (4) | (5) |
(1) Project number |
|
(2) Unit/area code |
|
(1)Drawing lead number |
|
(2) Suffix |
|
(3) Serial number |
|
The lead drawing of a subject will be identified with suffix character A, the next drawings of the same subject will be given consecutive characters. If the characters run out of the alphabet double characters will be applied e.g., AA, AB, etc. DO NOT use the characters I or O.
For numbering of bar bending schedules and HVAC drawings see following note:
Note:
- All drawings prepared for Heating, Ventilation and Air Conditioning (HVAC) will have the same number as the pertaining architectural drawings with suffix AA.
- For bar bending schedules use suffix characters "S" after the lead drawing number, e.g., 1111-0002401A-S1, S2, S3 etc.
For assigning isometric numbers refer to section 4.5.2 and Attachment 3, note 1.
For assigning numbers to piping MTO input forms see ref. 5.2.
Examples:
1111-5500151A | Plot Plan Effluent Treatment |
1111-5500151B | Plot Plan Sludge Treatment |
1111-0012107A | Lead Engineering Flow Diagram for Unit 12 |
1111-5550107A | Lead Engineering Flow Diagram for Unit 5550 |
4.5.2 Isometric Drawing Numbering Format
NNNN | — | NNNN | NNN | — | A | NNN |
(1) | (2) | (3) | (4) | (5) |
(1) Project number |
|
(2) Unit/area code |
|
(1) Drawing lead number |
|
(2) One alpha character |
|
(3) Drawing sequence numbers |
|
Example: | |
1111-0162155-D021 |
4.5.3 Multi Sheet Documents
Multi sheet documents will carry one general document number as described under 4.5.1 followed by consecutive sheet numbers.
4.6 Planning Documents
NNNNNN | — | "AA" | A | — | NN | NNN | (A) |
(1) | (2) | (3) | (4) | (5) | (6) |
(1) Project Contract number |
|
||
(2)Planning prefix |
|
||
(1)Planning indicator |
|
||
Barchart - B Curve - C Histograms - H Keydate schedules - K Logic’s diagrams - L Manpower - M Networks - N Progress - P Reports - R | |||
(4)Unit code |
|
||
(5)Serial number |
|
||
000 - | 009 | Management Level | |
010 - | 099 | Overall level | |
100 - | 999 | Detail level | |
100 - | 199 | HO Engineering | |
200 - | 299 | Client | |
300 - | 399 | Authority | |
400 - | 499 | Commissioning | |
500 - | 899 | Outside Services | |
900 - | 999 | Construction | |
(6) Suffix |
|
Planning documents only issued as part of a progress report will get the progress report number.
Example: | |
111110-PLC-50201 |
|
111120-PLC-50201 |
|
4.7 Sketches
NNNN | — | "AA" | — | A(A) | NN | NNN | (A) |
(1) | (2) | (3) | (4) | (5) | (6) |
(1)Project number |
|
(2) Sketch prefix |
|
(3) Project cost code |
|
(4)Unit code |
|
(5) Serial number |
|
(6) Suffix |
|
Each discipline shall keep an up-to-date record of the sketch numbers used.
Sketches only issued as part of a specification/requisition will get the specification/ requisition number.
Example: | |
1111-SK-D50010A |
|
1111-SK-Ch40001A |
|
4.8 Calculations
Basic structure of calculation identification.
NNNN | — | “AAAA” | — | A(A) | NN(NN) | NN(N) | (A)A |
(1) | (2) | (3) | (4) | (5) | (6) |
(1) Project number |
|
(2)Prefix |
|
(3)Project cost code |
|
(4)Unit/area code |
|
(5) Calculation number |
|
(6) Suffix |
|
The number shall refer to the specifics of the calculation, e.g., calculation related to a tower shall be identified by its equipment number, electrical calculations can refer to a project cost code whereas a structural calculation shall be related to a drawing number.
For design calculations the character "Z" is added to the related drawing number.
Refer to Attachment 3 for the assignment of calculation numbers for authority engineering, process and control systems.
The elements of the basic structure are to be selected for the relevancy of the subject.
Examples: | |
1111-CALC-AS1201A |
|
1111-CALC-ET01 |
|
1111-CALC-E01 |
|
1111-CALC-0010734ZE |
|
5. References
Document Number | Title | Level | |
5.1 |
CM-PE-500 | Preparation and Handling of Requisitions | 2 |
5.2 |
BN-G-UE202 | Bulk Material Management Execution Plan and Procedures (Attachment “H”) | 5 |
5.3 |
CM-PE-504 | Production of Engineering Documents | 2 |
5.4 |
BN-S-UK001 | Project Procedure and Execution Manual (Standard) | 5 |
5.5 |
CM-PE-706 | Vendor Print Control | 2 |
5.6 |
BN-EP-240 | Administrative Management of the Engineering Department | 3 |
5.7 |
CM-MA-114 | Allocation of Charge Numbers | 2 |
Refer to BN-W-UE301_att